Prior to the intervention. The premises of yacht clubs, which cluttered the port with architectural and visual barriers, blocked public access to 80% of the docks area where, moreover, the fact that priority was given to cars, discouraged pedestrian use.

BEFORE

images  (10)

AFTER
 

description

previous state

With an area covering 25 hectares and space for more than 3,200 boats, the Old Port of Marseilles is Europe’s largest docks area in an urban setting. The foundational site of the capital of Provence, it was also the region’s economic centre until midway through the nineteenth century when transport of goods and passengers was moved northwards to the Grand Port Maritime (Great Seaport) of Marseille. With a narrow entrance flanked by two old fortifications, the Vieux-Port occupies a natural bay around which, structured by the Avenue de la Canebière, the central districts of the city have been built.

However, despite its central location and the beauty of its geographic setting, the port fell into neglect and a state of disrepair by the end of the twentieth century. The premises of yacht clubs cluttered the port, occupying 80% of its surface with unauthorised constructions and imposing architectural and visual barriers everywhere. Moreover, the fact that priority was given to private vehicles, discouraged pedestrian use in a considerable part of the docks area. In the central wharf, Quai des Belges (otherwise known as Quai de la Fraternité), there were nine lanes for vehicular transport, while the Quai du Port (at the northern end) and the Quai de la Rive Neuve (in the south) had six lanes each.

aim of the intervention

In 2009, four years before Marseilles was to become the European Capital of Culture, the City Council and the Marseille Provence Métropole (MPM – Urban Community of Marseille Provence Métropole) approved a budget of 45 million euros with a view to renovating the port. They called for entries in a competition aimed at restoring the former dignity and grandeur of the old port. In a first phase, 36 million euros were to be spent on refurbishing the three wharves. Besides endowing the city with an area large enough for crowd-pulling events, a further objective was to considerably reduce the impact of traffic and opt for more sustainable and egalitarian systems of public transport. The second phase of the project, which is to begin in 2016, will work on improving the public spaces of the neighbourhoods adjacent to the port.

description

 The first phase of the renovation work has cleared obstacles and vehicular transport from the 12,000 square metres occupied by the port’s three wharves, which are now uniformly paved in pale granite evoking the original limestone cobblestones. The central Quai des Belges, now devotes 60% of its surface to pedestrians and protects them from the sun beneath the Grande Ombrière, a rectangular canopy of 1,000 m2, which can also be used for large-scale events with big audiences. New floating docks have been installed in order to accommodate water activities without interfering with the pedestrian flow or views.

assessment

Thanks to a consultative process, which took into account the suggestions of residents, businesspeople and local associations before calling for entries in the competition, the port has recovered its vitality by means taking the general interest into account. The presence of leisure craft, which fosters economic and associative activity, has been made compatible with access for all citizens and their recreational activities. Hence, while other city ports combat economic decline by allowing privatised, excluding enterprises that undermine their role as public space, the Vieux-Port has been renovated by expanding its condition of a shared space that is open to everyone.

David Bravo
Translation by Julie Wark

Comment and vote the work

Vote
Average rating: 4.1 / Votes: 6
 
Comments

We shall publish your views on-line as soon as possible. All comments will be reviewed by a moderator in order to avoid abuse. Thank you for participating.

Send your comment »
Please type the text presented in the image:
The Grande Ombrière a rectangular canopy of 1,000 m2, protects pedestrians on the Quai des Belges from the sun, and can also be used for large crowd-pulling events.  © Young Foster Partners

technical sheet

CITY: Marseille (768,999 inhabitants)

COUNTRY: France

BEGINNING OF THE PROJECT: 2011

BEGINNING OF WORK: 2012

END OF WORK: 2013

AREA: 12,000 m2

COST: 45,000,000 €

credits

DEVELOPER:

Marseille Provence Métropole (MPM) - Direction des Infrastructures

AUTHORS:

Michel Desvigne Paysagiste MDP, Foster + Partners, TANGRAM, INGEROP, AIK AIK

COLLABORATORS:

Justine Miething, Lorenzo Mayer, Spencer de Grey, Jürgen Küppers, Max Neal, Emmanuel Dujardin, Cedric Geeart, Jerome Guigon, Romain Verdet, Anne-Laure Boichot, Pascal Mahieu, Olivier Poulet, Ludovic Gautier, Charles Henri Lear, Yann Kersalé, Jean-Marie Priol